Contenido del curso
Módulo 2: Gestión del alcance y aliados de un proyectos
Módulo 3: Gestión del Cronograma de un proyecto
- 11

How Project Schedule Management Works
03:02 min - 12

Dependencias entre actividades para cronogramas de proyecto
06:46 min - 13

Effort vs Duration: The PERT Method
Viendo ahora - 14

Ruta crítica y cronograma con diagrama de Gantt
05:58 min - 15

PERT and ClickUp for Project Scheduling
07:56 min - 16

Técnicas de compresión de cronogramas: fast tracking y crashing
09:03 min
Módulo 4: Planificación y Presupuesto de Costos
- 17

Gestión de costos en proyectos: procesos del PMBOK y control
04:23 min - 18

Tres métodos para estimar costos de proyectos con precisión
07:34 min - 19

Presupuestos de proyecto con reservas y curva S para control financiero
09:55 min - 20

Building a Project Budget Baseline With S-Curve
07:15 min - 21

Why Low Spending Can Hide Project Failure
11:58 min - 22

WSJF and ROI to Prioritize Projects
06:58 min
Módulo 5: Siguientes Pasos
Effort vs Duration: The PERT Method
Resumen
Estimating effort and duration is the bridge between planning and execution in project management. Once you've defined your scope, built your work breakdown structure (WBS), and sequenced activities, the next question becomes unavoidable: how much time and how many resources will each activity actually need? Promising dates without a solid capacity base is like taking off without fuel. Reality will catch up.
Good estimates blend hard data with the inevitable uncertainty of any project. The core idea here is to separate effort from duration, and to understand the real capacity of your team before committing to a schedule.
What is the difference between effort and duration?
These two terms get confused all the time, and that confusion is exactly where unrealistic schedules are born.
Effort is the total amount of work required to complete an activity, usually measured in person hours or person days. For example, designing the circuit of a drone could require 80 hours of effort from one engineer.
Duration, on the other hand, is the calendar time needed to finish that activity. It depends on the total effort and the resources assigned. If those 80 hours are handled by a single full time engineer working 8 hours a day, the duration is 10 days. Add engineers in parallel and the duration shrinks, even though the effort stays the same.
What is effort in project management? It's the total work needed to finish a task, measured in person hours or person days. It doesn't change with how many people you assign.
What is duration in project management? It's the calendar time a task takes from start to finish. It depends on effort divided by the capacity of the resources working on it.
How does the PERT three point estimation technique work?
When you have little historical data, a single number estimate is risky. The PERT technique, also called three point estimation, helps you handle that uncertainty by considering three scenarios for each activity.
- The optimistic estimate is the best case if everything goes perfectly.
- The most likely estimate reflects realistic conditions.
- The pessimistic estimate is the worst case if things go wrong.
The formula for the expected effort or duration is: optimistic plus four times the most likely, plus pessimistic, divided by six. The result is a weighted average that softens estimates that lean too optimistic or too pessimistic.
How do you apply PERT to a real work package?
Let's use the autonomous drone project to make this concrete. Imagine you need to estimate the effort for the GPS module integration package.
- Optimistic: 16 hours if the component is plug and play and there are no compatibility issues.
- Most likely: 32 hours, including some software adaptation and calibration.
- Pessimistic: 64 hours if firmware problems, hardware errors, or custom drivers appear.
Applying the PERT formula: 16 plus 4 times 32 plus 64, divided by 6, gives you 34.67 hours, which you can round to 35 hours of expected effort.
What is the PERT formula? It's (optimistic + 4 × most likely + pessimistic) / 6. It produces a weighted average expected value that reduces the impact of extreme scenarios.
How do you turn effort into a realistic duration?
Knowing the effort isn't enough. You need to translate it into calendar time using the real capacity of the people doing the work.
Suppose one firmware engineer is assigned to the GPS task. After discounting meetings and interruptions, their effective capacity is 25 hours per week. The duration equals the estimated effort divided by capacity per unit of time: 35 hours divided by 25 hours per week equals 1.4 weeks.
The effort is still 35 hours, but the real calendar duration for that engineer is about a week and a half. If you had several engineers working in parallel and the work could actually be split, the duration would drop while the effort stayed the same.
This distinction matters because assuming 100% dedication is one of the most common planning mistakes. Meetings, emails, breaks, and multitasking all reduce effective working time.
Why does precise estimation matter for your project?
A solid estimation practice changes how the entire project behaves. It gives you a base to plan dates that are actually achievable, instead of a fantasy schedule.
- You assign resources effectively, knowing how many people, tools, and materials you need and when.
- You manage stakeholder expectations with realistic dates and costs, avoiding surprises and building trust.
- You identify risks early, since estimating often surfaces dependencies, resource constraints, and uncertainties.
- You control progress against a baseline, comparing real execution to the plan and making corrections in time.
What is a practical action plan to start estimating?
Pick six to ten work packages from your WBS and run each one through PERT. For every package, gather an optimistic, most likely, and pessimistic estimate, then calculate the expected effort.
Next, calculate the real capacity of your team. Don't assume full dedication. Subtract meeting time, emails, breaks, multitasking, and anything else that erodes effective work hours.
Finally, validate the numbers with the people who will actually execute the task. Their experience is invaluable, and the best estimates always come from those closest to the work. Have you tried PERT on your current project? Share how it went in the comments.